Expect delays on roadways and waterways as another phase of construction gets underway on the new Johnson Street Bridge.
Work to lift and place the 46-meter bridge deck span across new Johnson Street Bridge begins this Friday.
Jonathan Huggett, Johnson Street Bridge project director, says mother nature needs to behave in order for work to proceed.
The massive crane dubbed 'The Dynamic Beast' will land in the upper harbouragain later this week to help with the heavy lifting.
The machine was last in the harbour in December.
Crews anticipate the marine channel will be closed for about nine days beginning this Friday.
There will be traffic disruptions too, including the closure of the existing JSB next weekend to all traffic.
All the details and a live webcam can be found at: https://www.johnsonstreetbridge.com/